Quick answer
If your change of use approval is delayed and rent has already started, do three things this week: confirm which pathway you're on (exempt, complying development or a development application), ask council or your certifier for a written timeline, and ask the landlord to move rent commencement to approval. Then work out the weekly cost of waiting — rent, repayments, wages, insurance — and fund that gap with working capital rather than your fit-out budget.
Key points
- Your pathway decides your timeline — exempt, complying development and a full DA run on very different clocks
- Put a weekly dollar figure on the delay before you talk to the landlord or a lender
- Rent commencement tied to approval is the single most valuable lease clause for a business that needs a permit
- Don't let the fit-out budget quietly become the rent budget — fund the waiting period separately
- Ask for written timelines from council or your certifier and keep every request-for-information response fast
If your change of use approval is delayed and the rent has already started, you’re not stuck, but the clock is costing you money every week. Do three things now: confirm which approval pathway you’re on, get a written timeline from council or your certifier, and ask the landlord to move rent commencement to the approval date. Then fund the waiting period on purpose.
This is the point where an opening timeline breaks. The lease is signed, the shopfitter is pencilled in, and a piece of paper nobody controls has become the thing that decides when you earn your first dollar. Here’s how to work through it.
Which approval pathway are you actually on?
Most delays come from being on a slower pathway than the owner assumed. In NSW there are three, and the NSW Planning Portal sets out the order:
| Pathway | What it means | Why it matters for your timeline |
|---|---|---|
| Exempt development | No planning approval needed if the change meets the exempt rules | Fastest — but narrow |
| Complying development (CDC) | A council or private certifier checks your plans against fixed standards | Usually quicker than a DA, with a certifier you can chase |
| Development application (DA) | Council assesses the proposal on its merits | Slowest, with referrals and possible public notice |
The exempt rules are tight. Among the conditions on the Planning Portal: the new use must sit in the same business category as the old one, the current use must be lawful, the new use must be permitted in the zone, floor area can’t grow and the building must already meet fire safety and building code requirements. Moving between types of retail shop is treated as a change of tenant, not a change of use. Food and drink premises and beauty salons are excluded from exempt development, and so are sites in heritage conservation areas or listed as State heritage items.
Other states use their own systems. In Victoria, for example, the equivalent step is often a planning permit, and the rules sit with the local council and Planning Victoria. The principle is the same: the pathway you’re on sets the clock.
First move: ask your certifier or council planner, in writing, which pathway applies to your exact use and address, and what the next step is. If you’ve been waiting on the wrong pathway, it’s better to find out this week than in three months.
Why is council approval taking so long?
Rarely is it one thing. The usual culprits:
- A request for information. Council or your certifier asks for another report, a revised plan or a fire engineer’s letter. The clock often pauses while they wait for you.
- Incomplete lodgement. Missing plans, no owner’s consent from the landlord, or wrong documents mean the application sits in a queue before it’s formally accepted.
- Referrals. Fire, heritage, traffic or health teams review separately.
- Landlord consent. You usually need the owner’s signature on the application, and a slow landlord is a slow approval.
Your fastest lever is your own response time. Answer every request for information the same week, and keep a log of dates. In Victoria, councils have 60 statutory days to decide a planning permit application, and if they don’t, you can apply to VCAT for a failure-to-decide review. Planning Victoria’s guide covers how reviews work. But note the catch: the clock can stop when council asks for more information, so 60 days isn’t always 60 days. And VCAT has its own wait.
What is each week of delay really costing you?
Before you ring the landlord or a lender, put a number on it. A simple weekly “cost of waiting” list works:
- Rent and outgoings (and any GST)
- Loan or equipment repayments that have already started
- Insurance, utilities and security for an empty tenancy
- Wages for anyone you’ve already hired, plus super — with Payday Super in force from 1 July 2026, super is due with each pay run
- Deposits and holding fees on equipment or stock you can’t take delivery of
- Your own drawings, if the business is your income
Add them up, then multiply by the number of weeks council says it could take, and by a second figure that’s twice as long. That’s your delay range. It’s the number you take to the landlord and to a lender.
Illustrative example: an owner signs a lease for a shop they want to turn into a small clinic. Rent started at handover, the fit-out contract is signed, and the application needs more information from a fire engineer. The delay range is eight to sixteen weeks. Eight weeks of rent, outgoings, one hire and a repayment is already a real hole. Sixteen is the number they plan for.
Can you renegotiate the rent while you wait?
Often, yes. Landlords care about two things: a tenant who stays and a tenancy that’s improved. An approved change of use usually makes the property more valuable, so you have more leverage than it feels like.
What to ask for, in order of value:
- Rent commencing on approval, not on handover or lease start. This is the best outcome.
- An extended rent-free period that runs from approval, not from a fixed date.
- A staged start, for example outgoings only until approval, then full rent.
- A deferral, where missed rent is added back over the first months of trading.
- A conditional lease or a lease with a termination right if approval isn’t granted by a set date.
The best time to get these was before signing. In NSW, a landlord must give you a lessor’s disclosure statement at least seven days before the lease is entered into, according to the NSW Small Business Commission, and that’s the moment to ask whether approvals are needed and who is responsible. But if you’re past that, you can still ask. Bring the written timeline from council, evidence you’ve lodged properly and a proposal: “Rent starts at approval, and I’ll sign the extension we discussed.”
For lease rights specific to your state, the Victorian Small Business Commission and its NSW counterpart are the neutral starting points. Get a lawyer to write any variation. The definition of “approval” matters: granted, final and free of appeal are different things.
See where your cash gap really sits? Our funding planner lays it out in a few minutes, or you can start an enquiry when you’re ready to talk numbers.
What can happen on site while you wait?
Ask your certifier for a written answer, because the rules depend on your pathway and the works. As a rule, don’t start building work that needs approval before the right consent is in place. Some internal works are exempt, and some approvals cover use and building together. The expensive mistakes are stop-work orders and fines, and a landlord who now has a reason to push back.
Things that are usually safe to progress:
- Design, drawings and quotes
- Ordering long-lead equipment, with a delivery date that matches approval (hold the deposit, not the delivery)
- Hiring and training, timed to the revised opening date
- Supplier and insurance setup
If you’ve already paid a shopfitter a deposit, ask for the start date in writing and whether the contract can move. Tight contract dates and a floating approval date are how deposits get stuck. Our guide to moving into your first premises covers the lease terms that shape this, and the fit-out budget guide shows how to keep fit-out money separate from running costs.
How do you fund the gap without raiding the fit-out?
The mistake most owners make is letting the fit-out budget quietly turn into the rent budget. Keep the pots apart:
| Pot | What it covers | Typical funding fit |
|---|---|---|
| Fit-out | Builder, trades, joinery | Fit-out or secured finance, staged to progress payments |
| Equipment | Chairs, ovens, treatment tables, fixtures | Equipment finance with the asset as security |
| Waiting period | Rent, repayments, wages, insurance until you can open | Working capital sized to your delay range |
| First weeks | Stock, marketing, quiet-weeks cash | Working capital or a line of credit |
When a lender looks at a stalled opening, they’ll want the lease, the approval pathway and your written timeline, your cost to opening and a realistic path to takings. A plan that says “eight to sixteen weeks, here’s the evidence, here’s what I need to cover it” reads much better than “I just need some cash”. A cash flow forecast that shows the delay range in black and white helps.
Two further notes. Property-secured finance, where you or the business owns property, can be larger and faster than unsecured, and “$20k to $250k possible same day (property-secured)” is possible in the right circumstances. Smaller unsecured amounts can sometimes fund the same day too. And whatever you borrow, size it to the delay range plus a buffer, not just the best case.
A 7-day plan when approval stalls
- Day 1: Confirm your pathway in writing with council or your certifier.
- Day 2: Get a written list of outstanding information and answer it.
- Day 3: Add up the weekly cost of waiting and the delay range.
- Day 4: Send the landlord a variation proposal (rent from approval).
- Day 5: Ask the shopfitter and suppliers to move dates, in writing.
- Day 6: Update your cash flow forecast to a new opening date.
- Day 7: Decide how much of the gap you need to fund, and speak to a finance specialist.
Waiting on a council isn’t a reason to stall your business
Approvals are the part of opening a business nobody can fully control, and owners get through them every week. What you can control is how long the gap hurts. If you’ve done the sums and the delay range is bigger than your cash on hand, it’s worth finding out where you stand before the next rent payment, not after it.
Here’s how we handle it. Enquiring takes about 60 seconds, and your credit file isn’t touched just for asking. We don’t send your details to a pile of lenders, so your phone won’t light up. A real person reads what you’ve told us and calls you about your situation. Please fill the form in accurately, including the approval pathway and your delay range, so we can match the right option first time.
Frequently asked questions
Do I need change of use approval for my shop?
Not always. In NSW, moving between retail shop types counts as a change of tenant rather than a change of use, and some moves within the same business category (for example shop to office) can be exempt development. A change that crosses categories, such as retail to a gym or café, usually needs complying development or a development application. Food and drink premises can't use the exempt pathway, and neither can sites in heritage conservation areas. Check with your council or a certifier before you sign.
How long does change of use approval take?
It depends on the pathway, the council and how complete your application is. Complying development certificates can be issued by a private certifier and are usually faster than a development application, which goes through council assessment. In Victoria, the statutory clock for a planning permit is 60 days, but it pauses when council asks for more information. Ask council or your certifier for a realistic date in writing rather than relying on the headline number.
Can I stop paying rent while I wait for council approval?
Only if your lease says so. Rent obligations come from the lease, not from whether you can trade. If rent has started, you're generally liable unless the lease is conditional on approval or the landlord agrees to vary it. Many landlords will agree to a rent-free extension or a deferral if you ask early, show progress on the application and offer something in return, such as a longer term.
What if the lease was signed before I knew I needed approval?
Talk to the landlord straight away and ask for a variation: rent commencing on approval, an extended rent-free period, or a staged start. Have a lawyer or your state small business commissioner explain your options. Don't stop paying without advice, because a default can put your bond or guarantee at risk.
Can I start the fit-out before change of use is approved?
Be careful. Building work that needs approval can't lawfully start until the right consent is in place, and starting early can mean orders to stop work or fines. Some internal works are exempt, and some approvals cover use and works together, so ask your certifier exactly what can happen now and what has to wait.
Can I get a business loan to cover rent while I wait for approval?
Often, yes, if the opening is realistic. Lenders look at the signed lease, the approval pathway, your costs to opening and where repayments will come from. A working capital or property-secured loan sized to cover the waiting period, rather than a vague top-up, is easier to assess. Enquiring takes about 60 seconds and doesn't involve a credit check.
Do I need a lawyer to renegotiate the rent start date?
It's wise. A variation to a lease is a legal document, and the wording of 'approval' (granted, final, free of appeal) matters. Retail lease rules differ by state, so a lawyer or your state's small business commission can tell you what applies to your premises.